Horse Grazing Compartments

A few early shots as we are finishing phase 1 of a large project in Chelmsford.

 

Converting an arable field into horse grazing compartments – over 3500m of tornado horse wire with capping rail and electric strand.

 

All on our 15 year guaranteed posts. 1500m of water pipe buried and connected to 8 troughs on hardstandings. Over 2000m2 of track laid – soil dug out and bunded on site, crushed concrete laid and planings topped. 19 gates installed at angles to enable machinery access to paddocks without wasting more area on expensive tracks.

 

 

All completed from start to finish in 6 weeks!